Free Ends
Refer to the project drawing.
Lay the first Post at the start position
Attach a Run End Counterweight assembly to the first Post
Position the second Post
Attach a Counterweight to the second Post
Position the third Post
Position the fourth Post and attach a counterweight
Drop handrail and kneerail into cradle fittings
Repeat the procedure until completion
Check that the maximum spacing for posts is no greater than 2000mm
Check that the maximum spacing for Counterweights is no greater than 4000mm
Check that there is a Run End Counterweight and adjacent Counterweight at each end of a run
Check that the maximum spacing for Counterweights is no greater than 4000mm
Closed Installations
Refer to the project drawing
Lay the first Post at the start position
Attach a Counterweight to the first Post
Position the second Post
Position the third Post and attach a Counterweight
Drop handrail and kneerail into cradle fittings
Repeat the procedure until completion
Check that the maximum spacing for posts is no greater than 2000mm
Check that the maximum spacing for Counterweights is no greater than 4000mm